August 15th, 2025 Local News
Desloge, Mo. (KFMO) - Traffic is moving again on North State Street in Desloge after Missouri Department of Transportation crews reopened the roadway on Friday.
The work is part of the ongoing roundabout construction project, which officials say is now about 40 percent complete. MoDOT reports the project remains on schedule, with a targeted completion date of December 15.
The new roundabout is expected to improve traffic flow and safety in the area once finished.